Created 17 January 2018

The Project Steering Committee for OPSYS Track 1 (Results and Monitoring), chaired by Pierre Amilhat, held a meeting on 14 December 2017 where it approved the launch of a test phase in February with a restricted number of implementing partners selected by pilot EUDs and HQ units.

Each pilot EUD and HQ unit will identify a number of implementing partners that would be willing to participate in the test phase, on a voluntary basis, as follows:

  • 2 to 5 NGOs that are beneficiaries of grants in direct management, and
  • 1 or 2 consulting companies that are in charge of service contracts which enable capacity building and follow a logframe during implementation.

Objectives of the test phase

The following main functionalities of OPSYS will be tested:

 

NGO/Consulting company

OM

 

Provide access to lead implementing partners

Access the system

 

Provide access to other implementing partners (if relevant)

 

Create a logframe

 

Add a result

 

Add an indicator

 

Add a value

 

Submit logframe

Review logframe and/or approve logframe

 

Timeline

 

1

Selection of a group of NGOs and consulting companies

By 31 January 2018

2

Webinar with Implementing Partners to present OPSYS and launch the test phase

First week of February 2018

3

Test phase

Mid-February to end of February 2018

4

Feed-back on the test phase to EUDs and HQ units

1-2 March 2018 (one dedicated session)

5

Webinar: feed-back on the test phase with Implementing Partners

Mid-March 2018